İstanbul International Finance Center Central Bank of the Republic of Türkiye Campus Phase 2

The tallest building in Europe

As of the end of 2024, 98.5% of the construction works for Phase 2 of the project, located within the İstanbul Financial Center and comprising a 59-storey building with a gross floor area of 350,000 square meters above ground, have been completed.

Within the scope of Phase 2 interior works, the progress rates are as follows: construction works at 99%, MEP works at 98%, and professional sound and lighting systems at 96%. The testing and commissioning processes for Phase 2 have reached a progress level of 92%.

In addition to the contractual works, demolition and reconstruction activities arising from revisions instructed by the Client are being carried out concurrently.

The completion of all Phase 2 works is scheduled for the first half of July 2025.