The project, representing the second tender package for the construction of Kuwait International Airport, features a parking facility with a total capacity of 5,127 vehiclesincluding 4,747 passenger spaces and 380 VIP and staff spaces-distributed across three basement levels and a mezzanine.

Covering a construction area of approximately 325,000 square meters, the project also incorporates over 700,000 square meters of landscaping and environmental design areas. Key components include two shelters, each spanning 11,000 square meters and equipped with three escape tunnels; three rainwater storage tanks with capacities of 12,000 cubic meters each, and one tank with a capacity of 14,000 cubic meters; a wastewater treatment plant with a daily capacity of 2,500 cubic meters; and a high-standard, climate-controlled warehouse building covering 4,000 square meters. The vertical and horizontal transportation system features 24 passenger elevators, 32 moving walkways, 48 escalators, and 8 freight/trolley elevators. Additionally, the project encompasses 240,000 square meters of terminal access roads, 8 bridges, 2 viaducts, and a 2.8-kilometer retaining wall, with the visible surfaces of the parking garage and retaining walls designed as landscaped areas.
Low-voltage systems were activated in May 2025. The layout of the connecting corridor (Link area) between the parking garage and the terminal building, as well as the VIP entrance area (Amiri Diwan), has been finalized, subject to final administrative approvals. The project is scheduled for completion by the end of 2026.