Central Bank of the Republic of Turkey Campus Phase I-II

The tallest building in Europe

As of the end of 2024, construction of the 59-story above-ground building with a gross area of 350,000 square meters, which is under construction at the Istanbul International Finance Center was 99.06% completed in Phase I and 97.42% completed in Phase II.

As part of tha Phase I shell and core works, the facede and civil works have been fully completed, while MEP installations have reached 99.68% completion, and elevator installations are 100% completed. In Phase II interior works, civil works are 99.25%, MEP installations stand at 93.40%, and professional sound and lighting systems are 95% complete.

Testing and commissionin activities for both phases have reached 70% progress.