As of the end of 2024, 98.5% of the construction works for Phase 2 of the project, located within the İstanbul Financial Center and comprising a 59-storey building with a gross floor area of 350,000 square meters above ground, have been completed.
Within the scope of Phase 2 interior works, the progress rates are as follows: construction works at 99%, MEP works at 98%, and professional sound and lighting systems at 96%. The testing and commissioning processes for Phase 2 have reached a progress level of 92%.
In addition to the contractual works, demolition and reconstruction activities arising from revisions instructed by the Client are being carried out concurrently.
The completion of all Phase 2 works is scheduled for the first half of July 2025.