Kahramanmaraş-Göksun 6th Region Border Road Section II

2016

The construction works for the second part of the project, which is 23.38 kilometers long in total, have been started on November 1, 2011.

The scope of the 23.38 kilometers long project includes the construction of 4 double-tune tunnels of total 5 thousand 362 meters in length, and four viaducts of total 1263 meters in length.

In the 13.4 kilometers section where the works have been conducted, 7 thousand 500 meters of divided road, 3 double-tube tunnels of 4 thousand 556 meters in length and two viaducts of 570 meters in length have been completed and taken into service.

The project has been completed and handed over to the General Directorate of Highways.